Tabel 2-5 Koreksi Kedua Aliran Gas Pada LOOP-1
RUAS PIPA
|
K.L
|
Q
|
I KQ I
|
KQ2
|
ΔQ
|
Q Baru
|
1 – 2
|
0.0831
|
1616.2
|
134.2724
|
217007.9
|
-12.2
|
1604.0
|
1 – 6
|
0.0415
|
-2233.8
|
92.7933
|
-207283.9
|
-12.2
|
-2246.0
|
2 – 5
|
0.0034
|
-921.2
|
3.1194
|
-2873.7
|
-12.2
|
-933.4
|
5 – 6
|
0.0051
|
-483.8
|
2.4574
|
-1188.9
|
-12.2
|
-496.0
|
JUMLAH
|
232.6424
|
5661.3
|
Tabel 2-6 Koreksi Kedua Aliran Gas Pada LOOP-2
RUAS PIPA
|
K.L
|
Q
|
I KQ I
|
KQ2
|
ΔQ
|
Q Baru
|
2 – 3
|
0.1039
|
787.4
|
81.7735
|
64389.9
|
-3.2
|
784.3
|
2 – 5
|
0.0034
|
933.4
|
3.1606
|
2950.1
|
-3.2
|
930.3
|
3 – 4
|
0.1080
|
-962.6
|
103.9631
|
-100073.1
|
-3.2
|
-965.7
|
4 – 5
|
0.0071
|
2187.4
|
15.5540
|
34023.1
|
-3.2
|
2184.3
|
JUMLAH
|
204.4513
|
1290.0
|
Tabel 2-7 Koreksi Ketiga Aliran Gas Pada LOOP-1
RUAS PIPA
|
K.L
|
Q
|
I KQ I
|
KQ2
|
ΔQ
|
Q Baru
|
1 – 2
|
0.0831
|
1604.0
|
133.2615
|
213752.7
|
-0.1
|
1604.0
|
1 – 6
|
0.0415
|
-2246.0
|
93.2988
|
-209548.2
|
-0.1
|
-2246.0
|
2 – 5
|
0.0034
|
-930.3
|
3.1499
|
-2930.2
|
-0.1
|
-930.3
|
5 – 6
|
0.0051
|
-496.0
|
2.5192
|
-1249.5
|
-0.1
|
-496.0
|
JUMLAH
|
232.2293
|
24.8
|
Tabel 2-8 Koreksi Ketiga Aliran Gas Pada LOOP-2
RUAS PIPA
|
K.L
|
Q
|
I KQ I
|
KQ2
|
ΔQ
|
Q Baru
|
2 – 3
|
0.1039
|
784.3
|
81.4459
|
63875.0
|
0.0
|
784.3
|
2 – 5
|
0.0034
|
930.3
|
3.1501
|
2930.5
|
0.0
|
930.3
|
3 – 4
|
0.1080
|
-965.7
|
104.3039
|
-100730.2
|
0.0
|
-965.7
|
4 – 5
|
0.0071
|
2184.3
|
15.5316
|
33925.1
|
0.0
|
2184.3
|
JUMLAH
|
204.4314
|
0.4
|
Tabel 2-9 Koreksi Keempat Aliran Gas Pada LOOP-1
RUAS PIPA
|
K.L
|
Q
|
I KQ I
|
KQ2
|
ΔQ
|
Q Baru
|
1 – 2
|
0.0831
|
1604.0
|
133.2571
|
213738.4
|
0.0
|
1604.0
|
1 – 6
|
0.0415
|
-2246.0
|
93.3010
|
-209558.2
|
0.0
|
-2246.0
|
2 – 5
|
0.0034
|
-930.3
|
3.1501
|
-2930.5
|
0.0
|
-930.3
|
5 – 6
|
0.0051
|
-496.0
|
2.5194
|
-1249.8
|
0.0
|
-496.0
|
JUMLAH
|
232.2276
|
0.0
|